10 free, exam-style Certified Compensation Professional (CCP) practice questions with answers and
explanations. No signup required. Work through them below, then take the
full free CCP practice test to study every exam domain.
These 10 free CCP questions are organized by exam domain, so you can see how each part of the Certified Compensation Professional blueprint is tested. Reveal the answer and explanation under each question.
Domain 1: Total Rewards Management 12.5% of exam
Question 1
An estimator is preparing a cost estimate for a new 150,000 barrel-per-day refinery. A similar 80,000 barrel-per-day refinery was completed two years ago at a cost of $600 million. Using the six-tenths rule and ignoring escalation, the estimated cost of the new facility is CLOSEST to:
- $822 million
- $1,125 million
- $875 million
- $932 million
Show answer & explanation
Correct answer: C - $875 million
Question 2
According to AACE Recommended Practice 18R-97, a cost estimate prepared when 5% to 15% of project definition is complete, typically used for feasibility studies and based primarily on equipment-factored or parametric methods, is classified as:
- Class 5
- Class 3
- Class 2
- Class 4
Show answer & explanation
Correct answer: D - Class 4
Question 3
A company is evaluating two mutually exclusive projects. Project A has an IRR of 22% and an NPV of $180,000 at the company's MARR of 12%. Project B has an IRR of 19% and an NPV of $240,000 at the same MARR. Which decision criterion should govern the selection?
- Select Project A because its IRR exceeds Project B's IRR
- Select Project B because its NPV is higher at the MARR
- Select Project A because it exceeds the MARR by a greater margin
- The projects cannot be compared without incremental analysis
Show answer & explanation
Correct answer: B - Select Project B because its NPV is higher at the MARR
Question 4
An asset is purchased for $200,000 with a salvage value of $20,000 and a useful life of 5 years. Using the double declining balance (DDB) method, the depreciation expense in Year 2 is:
- $48,000
- $80,000
- $36,000
- $57,600
Show answer & explanation
Correct answer: A - $48,000
Question 5
A project team is developing a contingency estimate using Monte Carlo simulation. The simulation output shows a P50 value of $8.2 million and a P80 value of $9.5 million. The deterministic base estimate is $7.8 million. If management approves funding at the P80 confidence level, the contingency amount is:
- $400,000
- $1,300,000
- $1,700,000
- $2,100,000
Show answer & explanation
Correct answer: C - $1,700,000
Domain 2: Quantitative Principles in Compensation Management 12.5% of exam
Question 6
A project has a Budget at Completion (BAC) of $2,000,000. At the end of Month 8, the Earned Value (EV) is $900,000 and the Actual Cost (AC) is $1,050,000. The Cost Performance Index (CPI) has remained stable at approximately 0.857 for the past four reporting periods. Using the cumulative CPI method, the Estimate at Completion (EAC) is CLOSEST to:
- $2,150,000
- $2,334,000
- $2,450,000
- $2,100,000
Show answer & explanation
Correct answer: B - $2,334,000
Question 7
At Month 10 of a construction project, the following EVM data is reported: PV = $750,000, EV = $680,000, AC = $710,000. Which statement BEST describes the current project status?
- Behind schedule and over budget
- Ahead of schedule and under budget
- Behind schedule and under budget
- Ahead of schedule and over budget
Show answer & explanation
Correct answer: A - Behind schedule and over budget
Question 8
A risk analyst assigns a PERT three-point estimate to a cost element: optimistic = $40,000, most likely = $55,000, pessimistic = $100,000. The standard deviation of this estimate is CLOSEST to:
- $15,000
- $7,500
- $20,000
- $10,000
Show answer & explanation
Correct answer: D - $10,000
Domain 3: Market Pricing - Conducting a Competitive Pay Analysis 12.5% of exam
Question 9
A project schedule network has three activities on the critical path: A (4 days), B (12 days), and C (6 days) in sequence. Activity D (5 days) runs in parallel with B, starting after A finishes (finish-to-start) and finishing before C starts (finish-to-start). The total float for Activity D is:
- 0 days
- 2 days
- 7 days
- 12 days
Show answer & explanation
Correct answer: C - 7 days
Question 10
An owner enters into a Fixed Price Incentive Fee (FPIF) contract with a target cost of $500,000, a target fee of $45,000, and a sharing ratio of 70/30 (owner/contractor). The ceiling price is $580,000. If the contractor completes the work at an actual cost of $540,000, the contractor's final fee is:
- $45,000
- $40,000
- $27,000
- $33,000
Show answer & explanation
Correct answer: D - $33,000
The rest of the CCP blueprint
The CCP exam also covers these domains. Drill them in the full free practice test:
- Domain 4: Base Pay Administration and Pay for Performance 12.5% of exam
- Domain 5: Variable Pay - Improving Performance with Variable Pay 12.5% of exam
- Domain 6: Job Analysis, Documentation, and Evaluation 12.5% of exam
- Domain 7: Regulatory Environments for Compensation Programs 12.5% of exam
- Domain 8: Strategic Communication in Total Rewards 12.5% of exam